Capital budgeting: NPV, IRR and payback period

NPV, IRR and payback show from different angles whether an investment creates value. The three methods calculated and compared on one example.

A new machine, a new branch, a software transformation or an acquisition: every investment decision rests on whether cash spent today will come back as more cash in the future. Three basic measures are used to answer that question: net present value (NPV), internal rate of return (IRR) and payback period. All three are widely used, but they do not answer the same question and sometimes point in different directions. In this article I set out the steps of capital budgeting, how to calculate and interpret the three measures, and common mistakes, using a hypothetical example.

Get the cash flows right first

The step that comes before any valuation method — and affects the result most — is identifying the project’s cash flows correctly. The basic rules are:

  • Cash, not profit: depreciation is not a cash outflow; capital expenditure is a cash outflow when it is spent. The tax effect is calculated separately.
  • Only incremental cash flows: include cash flows that arise if the project goes ahead and would not arise otherwise. Overheads incurred with or without the project are excluded.
  • Exclude sunk costs: amounts already spent and not recoverable (such as a feasibility study) are not part of the decision.
  • Working capital: additional inventory and receivables the project needs are an outflow at the start and an inflow when released at the end.
  • Opportunity cost: if the project uses an asset the company could use for something else (such as vacant land), the asset’s alternative value is added to the cost.
  • Residual value: the sale value or continuing value of assets at the end of the project’s life.
  • Exclude financing flows: loan drawdowns and interest payments are not added to the cash flows; the cost of finance is reflected in the discount rate. Otherwise the cost of finance is counted twice.

A hypothetical example

The project and all figures below are hypothetical; the discount rate is chosen only to illustrate the calculation. The company is assessing a TRY 100 million investment in a production line. Incremental after-tax cash flows (including residual value and the release of working capital) are shown below. The discount rate (minimum acceptable return) the company uses for projects of this risk is 20%.

Year Cash flow (TRY million) Present value (20%) Cumulative cash Cumulative present value
0 −100 −100.00 −100 −100.00
1 30 25.00 −70 −75.00
2 35 24.31 −35 −50.69
3 40 23.15 +5 −27.55
4 40 19.29 +45 −8.26
5 30 12.06 +75 +3.80

1. Net present value (NPV)

NPV is the sum of all cash flows discounted to today at the discount rate. In the example NPV is about +TRY 3.8 million. The interpretation: after delivering the 20% minimum return, the project adds about TRY 3.8 million of value in today’s money. If NPV is positive the project is acceptable; between mutually exclusive projects, the one with the higher NPV is preferred.

NPV’s strength is that it gives the answer directly as value, in currency. Its weakness is sensitivity to the discount rate. For the example project:

Discount rate NPV (TRY million)
15% +16.64
20% +3.80
25% −6.91

A five-point change in the discount rate can reverse the decision. The basis of the discount rate should therefore be stated clearly and the result presented with a sensitivity table. I cover how to determine the cost of capital in capital structure and the cost of capital.

2. Internal rate of return (IRR)

IRR is the discount rate that makes NPV zero — the project’s own return. In the example IRR is about 21.7%. Because it exceeds the 20% minimum return, the project looks acceptable — the same conclusion as NPV.

IRR is attractive because it gives a percentage and does not require the discount rate to be set in advance. But it has three important limitations:

  • It ignores scale: a small project returning 40% can create less value than a large project returning 22%.
  • The reinvestment assumption: IRR implicitly assumes interim cash flows can be reinvested at the same rate. For high-IRR projects this may be unrealistic.
  • Multiple IRRs: if the sign of the cash flows changes more than once (for example a large decommissioning cost at the end), there may be more than one IRR, or none.

A hypothetical comparison: project X requires TRY 20 million and generates TRY 10 million a year for three years. Its IRR is about 23.4% and its NPV (at 20%) about TRY 1.1 million. Project A above has an IRR of 21.7% and an NPV of TRY 3.8 million. If the company can do only one of the two (say they use the same factory space), looking at IRR picks X and looking at NPV picks A. In terms of value creation the right answer is A, because it adds more absolute value. For mutually exclusive projects, NPV should be the decision criterion.

3. Payback period

The payback period shows how many years it takes for project cash flows to recover the initial investment. In the example, cumulative cash turns positive in year three; assuming even flows, payback is about 2 + 35/40 ≈ 2.9 years. Discounted payback — calculated on present values — is about 4 + 8.26/12.06 ≈ 4.7 years.

Payback is not a measure of value: it ignores all cash flows after payback. But it is an important risk indicator, especially under high uncertainty and for companies with limited liquidity: the faster cash comes back, the less of the project is exposed to uncertainty far in the future. Payback should therefore be used alongside NPV as an additional constraint, not instead of it.

The three measures together

Measure Question it answers Example result Watch out for
NPV How much value does the project create? +TRY 3.8 million Sensitive to the discount rate
IRR What is the project’s return? 21.7% Ignores scale
Payback How quickly is the investment recovered? 2.9 years (discounted 4.7 years) Ignores later cash flows

Although the example project looks acceptable, NPV is small relative to the investment (about 4%) and turns negative with a small rise in the discount rate. For a “borderline” project like this, the cash flow assumptions need to be challenged before deciding.

Scenarios and sensitivity

An investment decision based on a single cash flow forecast hides uncertainty. At a minimum, test the effect of sales volume and price, unit costs, a possible overrun on the investment amount, a delay in start-up and the residual value. Finding which variable brings NPV to zero (break-even analysis) focuses management’s attention on the most critical assumption. I explain the method in scenario and sensitivity analysis.

Consistency on inflation and currency

In high inflation, if cash flows are forecast in nominal terms (including inflation) the discount rate must also be nominal; if they are forecast in real terms (constant prices) a real rate must be used. The currency must be the same on both sides. The same rule applies to company valuation; I discuss it in valuing a company with discounted cash flow.

The link to financial reporting

The discounted cash flow logic used in capital budgeting also appears in financial reporting. Under IAS 36, an asset’s recoverable amount is the higher of its fair value less costs of disposal and its value in use, and value in use is the present value of the future cash flows expected from the asset, discounted at an appropriate rate. Consistency between the assumptions used in the investment decision and those used in later impairment tests matters for both management and audit. IFRS 13 defines fair value as the price that would be received to sell an asset between market participants at the measurement date — a different concept from entity-specific value in use.

Common mistakes

  • Adding interest expense to the cash flows and also discounting at the cost of capital (double counting)
  • Forgetting working capital needs and residual value
  • Including sunk costs in the decision
  • Deciding between mutually exclusive projects on IRR
  • Using the same discount rate for every project; a risky new-market project and an efficiency investment on an existing line do not carry the same risk
  • Not comparing actual cash flows after completion with the original forecast; I explain how to institutionalise that comparison in capex approval process

Conclusion

In capital budgeting, NPV measures value creation, IRR measures return, and payback indicates risk and liquidity. NPV should be the main decision criterion, with the other two as supporting information. But all three are only as reliable as the cash flow forecasts and the discount rate, so challenging assumptions and sensitivity analysis are an inseparable part of the decision. I cover what to watch when building models in financial modelling best practice. You can read about my investment appraisal and financial modelling work on the FP&A page.